May 12, 2008

Diavik’s first quarter update


by Jo Black

Diavik Diamond Mines Inc. (DDMI), operator of the Diavik Diamond Mine, provides the first quarter update.

Diavik continued to build on its strong safety record with zero lost time injuries, two medical treatments and an all injury frequency rate of 0.37 during the first quarter of 2008.

Diamond production from the A154 South pipe was 1.8 million carats, 31% lower than the same quarter last year due to lower ore grade and processed volumes. Mining activity is currently taking place from a low grade area of the A154 pipe. Extremely cold temperatures experienced in the first quarter affected equipment reliability and productivity, resulting in lower ore recovered and processed.

Diavik’s operations workforce averaged 793 workers during the quarter, with 67 per cent northern, of which half were Aboriginal. Diavik employed 22 northern trade apprentices during the period. Preparation of the new A418 open pit is continuing as planned, with diamond production expected to begin in the next quarter.

Underground development work remained largely on plan, advancing the approximately 20 kilometres of access tunnels and ventilation raises. Construction of surface infrastructure to support underground mining continues on the crusher and the paste backfill plant, and on the expansion of the water treatment and power plants. A fifth fuel tank was commissioned to meet the increasing electricity requirements of underground mining. Diamond production from underground is

scheduled to begin in 2009, and is expected to replace open pit mining by 2012.

In exploration, a large diameter reverse circulation drilling program was successfully conducted from the ice to obtain an additional bulk sample to better define the A21 kimberlite pipe, located near the existing mining operations. Results are pending. In addition, DDMI has mounted an aggressive exploration program on its substantial claim block around the mine site, with a budget of $10 million for 2008.

At December 31, 2007, Diavik’s ore reserve contained in the A154 North, South, and A418 pipes was 21.9 million tonnes grading 3.5 carats per tonne for 77.1 million carats contained. Diavik has produced 41.5 million carats since production began in January 2003.

Source : http://www.diavik.ca/

Story link: Diavik’s first quarter update



Add to Bookmarks:

ADD TO NETSCAPE     ADD TO DEL.ICIO.US     ADD TO DIGG     ADD TO FURL

ADD TO STUMBLEUPON     ADD TO YAHOO MYWEB     ADD TO GOOGLE     ADD TO SPURL



No Comments

No comments yet.

Sorry, the comment form is closed at this time.


Previous: « Dianor updates Leadbetter project
Next: Tahera provides update »

Visited 257 times, 1 so far today since July 6th 2007